Was at the house yesterday and the tiling is almost complete, just the grouting to be done. In the past week or so they have also done the electrical fit offs, aircon and heating vents have gone in, taps, outdoor powerpoints etc.
OUR CASTLE - Building the Metro 51 (now 53) by Carlisle Homes
THE HOME - THE METRO 51 by Carlisle Homes
The Display Home.....
Friday, October 29, 2010
Friday, October 15, 2010
Painting is Finished, tiling to begin!!!!!!!
Weekly update.
The painters finished on Thursday and the tilers are due to start on Tuesday. I am going to meet them at the house on Wednesday. The other half met the SS at the property on thursday and we are still on track for a late nov/early dec handover..............can't wait!!!! The stair rail had also been stained and looked awesome apparently. We chose the colour 'Charcoal" which is a very dark greyish brown from memory. Will go take a look today or tomorrow and take some piccies. And will definately post some this time :(
The painters finished on Thursday and the tilers are due to start on Tuesday. I am going to meet them at the house on Wednesday. The other half met the SS at the property on thursday and we are still on track for a late nov/early dec handover..............can't wait!!!! The stair rail had also been stained and looked awesome apparently. We chose the colour 'Charcoal" which is a very dark greyish brown from memory. Will go take a look today or tomorrow and take some piccies. And will definately post some this time :(
Friday, October 8, 2010
Painting is half way there!
So this weeks update is we have the house painted in first coat inside and a few areas of the facade have been painted also. Front door has had a coat, in the beautiful red colour we chose. Was a little nervous about it when we chose it , but I am really happy with how the colours are so far coming together!
Tuesday, September 28, 2010
EXCITING UPDATE!
We met with our SS yesterday and he told us we will have a handover date in the next few weeks for late November or early Dec. Can't beleive how fast it is all happening.
Friday, September 24, 2010
Plastering finished on the 20/9/2010
Been a bit slack with my updates but have had a lot of progress in the last couple of weeks. The plaster has been finished. Kitchen, laundry, ensuites, powder room and stair case has been installed. All internal doors, skirting and architraves have also been installed.
Wednesday, September 8, 2010
Bricking finished....plastering about to start
So they finished bricking the house yesterday. The cladding still yet to go on though. We have been told that our plastering will start on Friday, so very excited to see the house take shape and not be just a shell!